Production Planning (MCE120) Field Descriptions

How To

Use these fields to enter finished items planned for production.

1. Order

Select whether to display planned production in D-date or I-item order. Press Enter to default to D.

2. Beginning

If you selected to display planned production in date order, enter the beginning date to display.  

If you selected to display planned production in item order, enter the beginning finished item number to display. Press F2 to search for items.

In the browser in the lower portion of the screen, the program displays planned production in either date order (beginning with date entered) or item order (beginning with item entered).

You can select from the following functions:

Change a line-item

Add line-items

Insert line-items

Delete line-items

Stop line-item entry

Access Note Entry (SME710) for the item highlighted in BOM line item browser or for the BOM document line record highlighted in the line item browser.

Done   Ends Bill of Materials Entry and returns you to the Finished Item field. Press Done again to exit the program

 

To add a production item, complete following:

1. Specify the planned production date. Press Enter to default to the system date.

2. Specify the warehouse. The entry must be a valid warehouse. Press Enter to default to the warehouse assigned to the terminal.  

3. Specify the bill of material finished item number. The entry must be a valid finished item. If the item is already entered for the same date on a previous line, you must edit the current entry to change or delete.

4. Specify the quantity planned to produce.

5. Save the new requirements for producing the quantity of the finished item entered.

6. Press Stop when you are finished adding items.

Components-- Accesses Production Planning Requirements (MCE121) program, which is used to display the components, quantities needed for the finished item, as well as on hand, on order and committed component quantities. You can access Note Entry (SME710) for the BOM document line record highlighted in the line item browser or for the item highlighted in BOM line item browser. When requirements are displayed, an asterisk (*) next to the units indicates that the number of units required is greater than available (available = on hand - committed). Press Done to return to Production Planning.

Entering and displaying bill of material finished items planned for production

Adding finished items planned for production

Changing or deleting finished items planned for production