This program allows the user of the FACTS system to print up to five time periods of bill of material quantity requirements based on planned production. The user prints a listing of what is required to produce and what components are needed based on all planned production that has been entered in the BOM Planned Production Entry program. At the end of the report, the user may remove the planned production information, convert it to production or leave requirements alone.
The user has the option to:
Report information includes the following:
1. Beginning Item
Enter the beginning item to print. Select the icon to start with the item code on file. Press F2 or select the icon to perform a search.
2. Ending Item
Enter the ending item to print. Select the icon to start with the last code on file for the print order choice. Press F2 or select the icon to perform a search.
3. Item Description
Select whether to print item description 1, 2 or both as set in the Item F/M. Press Enter (CR) to default to item description 1.
4. Warehouse
Enter the warehouse to print requirements. The entry must be a valid warehouse. Press Enter (CR) to default to the warehouse assigned to the terminal. Press F2 or select the icon to perform a search.
5. Include Components
Select the checkbox to include requirements of the component items needed to produce the BOM items. Press Enter (CR) to default to unselected.
6. Groupings
Enter the number of date groupings to print (2-5). Press Enter (CR) to default to 5.
7. Auto Increment
Enter the number of days to be used for automatic date increments (0-99). Press Enter (CR) to default to 7. Press to manually enter the dates of time groupings.
8. Dates
Enter the ending date for the first date grouping. Press Enter (CR) or to default to the system date. If automatic increments are to be used, the next dates are calculated automatically. If automatic increments are not used, enter each group ending date up to the number of groups selected.
9. Check Report. Do You Wish To Remove Printed Records, Convert To Production Or Neither?
Enter whether to R-remove planned production records for the items just printed, C-convert planned production just printed to production tickets, or N-neither, where no updating occurs.