Formulation Requirements Report (MCR770)

This program allows the user of the FACTS system to print up to five time periods of formulation quantity requirements based on planned production. The user prints a listing of what formulas will be required to produce, what ingredients will be needed, what finished items are required to produce, and what packaging items are needed based on all planned production that has been entered in the Formulation Planned Production Entry program. At the end of the report, the user may remove the planned production information, convert to production or leave requirements alone.

The user has the option to:

Report information includes the following:

Use the following fields to print the Formulation Requirements Report:

1. Beginning Formula

Enter the beginning formula to print. Select the image\ex_allft.gif icon to start with the first formula code on file. Press F2 or select the image\find_shg.gif icon to perform a search.

2. Ending Formula

Enter the ending formula to print. Select the image\end.gif icon to start with the last formula code on file. Press F2 or select the image\find_shg.gif icon to perform a search.

3. Warehouse

Enter the warehouse to print requirements. The entry must be a valid warehouse. Press Enter (CR) to default to the warehouse assigned to the terminal. Press F2 or select the image\find_shg.gif icon to perform a search.

4. Include detail

Select the checkbox to include requirements of the ingredients, finished items and packaging items needed to produce the formulas. Press Enter (CR) to default to N.

5. Groupings

Enter the number of date groupings to print (2-5). Press Enter (CR) to default to 5.

6. Auto Increment

Enter the number of days to be used for automatic date increments (0-99). Press Enter (CR) to default to 7. Press image\add_shg.gif to manually enter the dates of time groupings.

7. Dates

Enter the ending date for the first date grouping. Press image\sysdate_shg.gif to default to the system date. If automatic increments are to be used, the next dates are calculated automatically. If automatic increments are not used, enter each group ending date up to the number of groups selected.

8. Check report. Do you wish to remove printed records, convert to production or neither?

Enter whether to R-remove planned production records for the formulas just printed, C-convert planned production just printed to production tickets, or N-neither, where no updating occurs.